When should a construction lien be recorded

When should a construction lien be recorded

Q.

When should a construction lien be recorded?

A.

In Florida, a construction lien must be recorded within 90 days of the contractor’s last day of work or materials being provided on that particular site. The lien must be recorded in the county where the property being improved is located. You cannot use corrective work to extend the timeframe. See Florida Statutes 713.08